Friday, June 5, 2015

Update

The exterior of the building is complete. Sidewalks are in, retaining walls are built, edging is in and black dirt is placed. 
















Wednesday, May 6, 2015

Update

Masons have finished brick by overhead door and are getting closer to wrapping up. 


The siders are moving along - now 50% done. 


Patio door accent walls are being painted.  


Bathroom flooring is going in. 


Granite window sills are being installed. 






Wednesday, April 29, 2015

Interior update

Third floor is being painted out. 





Second floor drywall is wrapping up. 




First floor insulation is nearly complete. 













Exterior Update

The exterior is starting to take shape. 


Wednesday, April 22, 2015

Tuesday, April 14, 2015

Update

The 3rd floor is almost completely drywalled and half the lightweight concrete floor on 3rd has been poured.


The siding has begun and almost all the trim on the windows and patio doors are complete. 




Tuesday, April 7, 2015

Update

3rd floor is insulated and drywall has begun.  2nd floor is ready to start insulating. 




Friday, March 20, 2015

Update

The roof is complete. 


Decks are nearly complete and brick is moving along. 









Friday, March 13, 2015

Update

The roof will be dried in Monday. 




Masonry is going around the building doing ground work. 



Concrete stairs and stoops are being poured. 


Windows are being installed and decks being built. 










Monday, March 2, 2015

Update

Half of the roof trusses are set and we are sheathing that portion. 


Tuesday, February 24, 2015

3rd floor update

Almost all the wall are built for the 3rd floor. Today we will start swinging roof trusses.