Foundation update
The foundation is complete and we are pouring the last of the pads for the pre-cast columns. Precast will start on Monday 10/27.
Wednesday, October 8, 2014
Foundation Update
A 3rd of the foundation has been poured and we are working on getting the next portion ready to pour.