Tuesday, December 16, 2014
Update
1st floor walls are nearly complete. We are prepping the 2nd floor trusses and pouring the basement garage floor.
Monday, December 8, 2014
Monday, December 1, 2014
Thursday, October 23, 2014
Foundation update
The foundation is complete and we are pouring the last of the pads for the pre-cast columns. Precast will start on Monday 10/27.
Wednesday, October 8, 2014
Foundation Update
A 3rd of the foundation has been poured and we are working on getting the next portion ready to pour.
Monday, September 29, 2014
Sunday, September 7, 2014
Friday, August 8, 2014