Friday, June 5, 2015

Update

The exterior of the building is complete. Sidewalks are in, retaining walls are built, edging is in and black dirt is placed. 
















Wednesday, May 6, 2015

Update

Masons have finished brick by overhead door and are getting closer to wrapping up. 


The siders are moving along - now 50% done. 


Patio door accent walls are being painted.  


Bathroom flooring is going in. 


Granite window sills are being installed. 






Wednesday, April 29, 2015

Interior update

Third floor is being painted out. 





Second floor drywall is wrapping up. 




First floor insulation is nearly complete. 













Exterior Update

The exterior is starting to take shape. 


Wednesday, April 22, 2015